Heating Plant with Steam Turbine, 1.83 MW

Design Engineering of a thermal power plant, Steam Turbine 1.83 MW, Mining Company

We completed a fully detailed Engineering of Project including PiD, flow diagrams, and workshop drawings.

Client: Mining Company 
Description:

Thermal power plant, 1.83 MW Steam Turbine 

Location: RU
Assignment:

Design Project of a new Power Plant.

Production: electricity, steam, hot water 

Area of operation:

Combined heating and power, electricity and automation process

Services:
  • General Design
  • PID, Heat balance diagrams, Steam flow diagrams
  • Piping and instrument diagrams
  • Pressure vessels and heat transfer equipment design
  • Specifications
  • Shop drawings and CAD drafting
  • Steel detailing
Used software:

Revit model, CAD drafting, 3D rendering, EPLAN model 

 

Steam Turbine ParametersParameterValue
Power Nominal kWt 1830
Power Max kWt 2030
Rpm Rpm 3000/3000
Steam pressure MPa 3,8
Temperature °С 440
Extraction steam pressure MPa 0,5
Extraction steam temperature °С 257
Extraction steam flow t/h 3
Backpressure MPa 0,2

We also considered:

• Operation of equipment in parallel mode with power system networks;

• Turbine generator protection systems;

• Synchronization system;

• An automation system for a turbogenerator unit has been developed that implements control, regulation and protection functions