Steam Electric Power Station, 9MW

Nitrogen Production, Electric Power Station with 9MWt Siemens Steam Turbine

 

Client: Nitrogen Plant
Description:

Electric Power Station with Condensing Steam Turbine 9MWt, 10,5kV.  

Location:

Georgia

Assignment:  Engineering Design, supplying Heat and Electricity, Steam supply   
Area of operation: Combined heating and power engineering, architecture, electricity and automation process 
Scope of Services: Process design, HVAC design, Steel Drafting, Concrete Drafting, Electric and Automation, PID, 3D rendering
Software: Revit, AutoCAD, EPLAN

The project was developed in 90 days.

The steam turbine is placed in a new building.

A cooling tower for working in the Condensing cycle.